noprint

Change Order Policy

Policy Statement

During the course of any capital building project, there will be times when a change is required to the original plans. These changes may arise as a result of environmental conditions not anticipated during the planning process (e.g. sub-surface conditions, changes in regulatory requirements, unforeseeable circumstances, hazardous materials, contaminated soil, new equipment specifications that were unknown prior to tender, omissions in the working drawings, interferences, etc.)

The purpose of the policy is to ensure that change orders are minimized and appropriately controlled during the process of a capital building project. The time for approving the revisions to the Contract must be minimized or the Contractor may claim a delay to the Contract Time or proceed with the original Contract Documents and then the Owner will face additional costs and/or delay costs. Time is of the essence.

Procedure
Approval and Reporting Process

A. Contract Adjustments less than $10,000 and cumulatively below $10,000 in any given month:

 
BOARD
STAFF
EXTERNAL
MoHLTC
 
Board
R&A
Pres
Dir. Env.
Arch.
Contractor
Architect Issues CCO*
M
X
P
A
 
Contractor's Quote
M
X
R
P
 
Adjustment
M
M
M
X
A
P
 
Architect Issues CO*
M
M
M
X
P
A
 

B. Contract Adjustments between $10,001 and $50,000 and cumulatively below $100,000 in any given month:

 
BOARD
STAFF
EXTERNAL
MoHLTC
 
Board
R&A
Pres
Dir. Env.
Arch.
Contractor
Architect Issues CCO*
X
X
P
A
 
Contractor's Quote
X
X
R
P
 
Adjustment
M
M
X
X
A
P
 
Architect Issues CO*
M
M
X
X
P
A
 

C. Contract Adjustments above $50,001 and cumulatively below $250,000 in any given month:

 
BOARD
STAFF
EXTERNAL
MoHLTC
 
Board
R&A
Pres
Dir. Env.
Arch.
Contractor
Architect Issues CCO*
X
X
P
A
A
Contractor's Quote
M
X
X
X
R
P
 
Adjustment
M
M
X
X
A
P
 
Architect Issues CO*
M
M
X
X
P
A
 

D. Contract Adjustments above $250,001:

 
BOARD
STAFF
EXTERNAL
MoHLTC
 
Board
R&A
Pres
Dir. Env.
Arch.
Contractor
Architect Issues CCO*
X
X
P
A
A
Contractor's Quote
X
X
X
X
R
P
 
Adjustment
M
M
X
X
A
P
 
Architect Issues CO*
M
M
X
X
P
A
 

 

Last updated: May 5, 2009